Generally in project management, it is very important to accurately estimate the cost of a project. It is even more necessary for management decision and control. Before a project comes on stream, the cost implications must be known well in advance and properly estimated. This serves as a guide to proper project management and control. Proper cost estimation will allow for proper planning of costs, allocation of resources to various units of a project, cost control and most importantly budgetary control.
Cost
Definitions and Principles
The word “cost” when used in accounting
conveys lots of meaning and so must be properly qualified. There are many types
of costs and part of our discussion in this unit is to properly discuss various
costs and see how they properly fit into the study of project management. It is
so because when we mention “cost”, we should clarify the type of cost we are
talking about.
Let us discuss the key types of
costs that are important for our study.
Direct
Costs
Direct costs are those costs which
are attributed directly to a job or project. For example, if an engineer spends
five hours to design an engineering column, then that time spent by the
engineer can be described as a direct labour and the cost can be recorded as a
direct cost to be charged directly to the design of the engineering column.
Factory
Costs
The concept of factory cost is
mainly applicable to manufacturing concerns. Factory cost is the total cost of
a job or project before the addition of a mark-up for the purpose of profit.
Factory costs will include the following:
Fixed
Costs
Fixed costs are those costs which
remain virtually unchanged and must continue to be incurred even though the
workload might fluctuate between zero and the maximum or installed capacity.
Fixed costs will generally include the following:
c.
heating
and electricity expenses
e.
maintenance
of building, etc.
Indirect
Costs
In an ideal setting like a manufacturing
facility, the provision of office accommodation, management, welfare services,
accounting, heating and lighting all constitute costs that must be incurred in
running the manufacturing facility. Others will include salaries and wages.
Generally, all these costs are
termed indirect costs or overhead costs.
ITEM |
# |
Iron flat sheets |
1,000,000 |
Brass rods |
2,000,000 |
Aluminium profiles |
3,000,000 |
Total cost of direct materials |
6,000,000 |
Direct Labour |
|
Design - engineering labour |
200,000 |
Manufacture - factory hands |
700,000 |
Total direct labour |
900,000 |
Overheads |
1,350,000 |
Total factory cost |
8,250,000 |
Mark up at 30% |
2,475,000 |
Market selling price |
10,725,000 |
Standard Labour Costs
Labour constitutes a very critical
component of project cost. It includes the labour of both junior and senior
personnel, engineers, accountants and the rest who are involved in a project.
When trying to estimate the labour cost for any project, it would be very
difficult to use the different rates of pay to be earned by every individual.
There might be two engineers engaged in a project but they may not be earning
the same salaries. Generally, in project management, it is advisable to use
standard costing to estimate the cost of labour.
For labour costs, it is convenient
to classify people according to some convenient rules based on the type of jobs
that they do.
For example, engineers in a project
may be averaged out to cost K1,000,000 per annum. Therefore, we can estimate
that the standard cost for an engineer for a project is K1,000,000 per annum.
That is the cost that will be imputed in the cost estimate for engineers.
Also, for accountants involved in a
project, there may also be the need to work out the standard cost for an
accountant. For example, we might estimate the standard cost for an accountant
to be K1, 500,000 per annum.
For all types of labour, we should
have estimates of the standard costs. It enables the project to be properly
cost.
Grade |
Those Included |
Comments |
Salary per annum ZMW |
01 |
Company Director |
- |
5,000,000 |
02 |
Divisional Heads |
Rank of general
manager |
4,000,000 |
03 |
Assistant Divisional
Heads |
Rank of assistant
general manager and above |
3,000,000 |
04 |
Management Cadre |
Rank of senior managers and above. Includes Senior engineers and architects |
2,500,000 |
05 |
Engineers |
Managers |
2,000,000 |
06 |
Technologists |
Deputy managers |
1,500,000 |
07 |
Draughtsmen |
Assistant managers |
1,500,000 |
08 |
Administrative |
Staff Clerks,
Secretaries etc. |
1,000,000 |
Overhead Recovery
In table 1, we saw the
cost structure for a simple manufacturing project. We easily computed the cost
of direct materials and also direct labour. We also recorded overheads. In
practical terms, direct labour costs are not difficult to estimate.
Direct labour cost is
equal to time recorded on a job multiplied by the standard hourly rate. So, how
can we recover overheads?
An amount can be added
that is proportional to labour cost (usually a percentage) to recover a part of
a company’s indirect overhead costs. In table 1, we saw total direct labour as
N900,000. Overheads standing at N1,350,000 is about 150% of total direct labour
costs. Generally, the method of recovering overheads as a levy on direct labour
costs is called absorption costing.
However, setting the
percentage overhead rate is a technical matter requiring professional
accounting skills.
Work
Breakdown
Consider a project to
build a new university Chibombo which is about 20 kilometres from Lusaka, the
Imo State capital. Even where we have defined the project as a new university,
it will be very necessary to consider the total picture of the new university
project.
The university project
will include the following:
a. access roads b.
administrative buildings c. lecture halls d. clinics e. laboratories f.
churches and mosques g. students hostels h. university teaching hospital
complex.
Breaking the total
project into smaller units constitutes what is referred to as a work breakdown.
Work breakdown enables the project managers or administrators to break down a
large or complex project into smaller and more manageable units.
The ideal thing to do
is to break a project into smaller units called subprojects. The sub-project
itself could be further divided into much smaller units for effective analysis
and design.
When a project is
broken down into smaller sub-projects, it becomes very easy to cost each
sub-project properly. After costing each subproject properly, then we could
then add up the costs of the sub-projects to generate the cost of the total
project.
In this article, we
discussed cost estimates: definition and principles. We discussed direct costs,
factory costs and fixed costs. We discussed standard labour costs and overhead
recovery. We also discussed the concept of work breakdown. All these have enabled
us to understand the basic principles of cost estimates.
Association of Cost Engineers.
(1991). Estimating Checklist for Capital Project. (2nd Ed.). London: Spon.
No comments:
Post a Comment